With the Fenton Phase 1 building shells nearing completion on Main Street, a total of 37 retail tenants have received permits to upfit their ground floor spaces. A few of the tenants are anticipating an opening date of May 1, and the developer is readying two parking decks and several temporary surface parking lots for customers. Work is also under way on the installation of final hardscape features like sidewalks and sitting walls, landscaping, signage, and the traffic signals at the Trinity Road intersection and I-40 ramps on Cary Towne Boulevard. A grand opening event is expected for the first weekend in June.
In addition, the developer is getting ready to construct the extension of Quinard Drive from Fenton to Southeast Maynard Road. Right-of-way and easement acquisition is now in progress. Construction is anticipated for late summer with a completion by fall of 2023.